Our teams are learning how the installation of sanitary sewer structures moves from design to construction.
CHW’s Construction Engineering Inspection (CEI) Department recently held an internal site visit with various disciplines and roles of the CHW team at the project site of Convergence Park Momentum Labs, a 54,800 square foot Biotech Research & Development Facility in Alachua, Florida. We were fortunate to have the expertise of Senior Inspector Don Lee and Construction Project Manager Christie McLelland to guide us through the site and educate the team on the installation process, equipment, and materials used during the construction of sanitary sewer structures. CHW team members observed the various phases of the installation process while learning all about pipe slopes, manholes, backfilling, shaping and excavating storm ponds, and the role CHW Construction Engineering Services plays during the construction process.
Thank you, Pinnacle Site Solutions, Theory Construction, and Concept Companies, for maintaining a safe project site and welcoming our team.